Civil works at the Mbudzi Interchange are reportedly progressing according to plan, with the project expected to be complete by July this year.

The construction Interchange project is currently at 59.4% of completion.

The interchange comprises of 15 bridges, 13 bridges are on the interchange and two bridges are off-site bridges in Amalinda Drive and Harare Drive.

The bridges on the interchange, about six of the bridges are substantially complete.