The Kazungula Bridge, spanning the Zambezi River between Zambia and Botswana, was designed as a combined road and rail bridge to enhance regional trade and connectivity. The plan for the rail track involves integrating it into the broader Mosetse–Kazungula–Livingstone Railway project, which aims to connect Mosetse in Botswana to Livingstone in Zambia, covering approximately 430 kilometers. Below is an explanation of the plan based on available information:

The Kazungula Bridge, connecting Botswana and Zambia over the Zambezi River, was a major infrastructure project with a long timeline. Here is a summary of the key milestones:
- 2001: A feasibility study for the bridge was conducted by Japanese consultants.
- 2012: The governments of Botswana and Zambia signed loan agreements with the Japan International Cooperation Agency (JICA) and the African Development Bank (AfDB) to co-fund the project.
- 2013: Bids for the bridge’s construction were invited.
- 2014: A groundbreaking ceremony was held on September 12, marking the official start of construction by the chosen contractor, Daewoo Engineering & Construction.
- 2018: The presidents of Botswana, Zambia, and Zimbabwe inspected the progress of the bridge. During this meeting, it was agreed that Zimbabwe would join the project in its second phase.
- Late 2020: The main bridge construction was completed, though some delays were experienced due to the COVID-19 pandemic. The one-stop border posts on either side of the bridge were also nearing completion.
- May 10, 2021: The Kazungula Bridge was officially inaugurated by the presidents of Botswana and Zambia.
Key Details of the Rail Track Plan
- Bridge Design and Rail Integration:
- The Kazungula Bridge, completed in May 2021, is a 923-meter-long, 18.5-meter-wide structure with a single railway line positioned between two road traffic lanes and pedestrian walkways.
- The rail track is currently unconnected to existing railway networks in both Zambia and Botswana but is designed to accommodate future rail traffic as part of the Mosetse–Kazungula–Livingstone Railway.
- Due to the bridge’s design, rail and road traffic cannot operate simultaneously; vehicles must stop to allow trains to cross, though this is still more efficient than the previous ferry system.
- Mosetse–Kazungula–Livingstone Railway Project:
- The railway project involves constructing a 430-km rail line, with 367 km from Mosetse to Kazungula in Botswana and 70 km from Kazungula to Livingstone in Zambia.
- The rail line aims to connect Zambia and Botswana, providing a shorter trade route from Lubumbashi in the Democratic Republic of Congo (DRC) to Durban Port in South Africa (2,860 km compared to 3,188 km via Beitbridge). It also offers an alternative to the structurally limited Victoria Falls Bridge.
- The project is expected to enhance regional integration within the Southern African Development Community (SADC) by facilitating trade to ports like Beira (Mozambique), Dar es Salaam (Tanzania), and Walvis Bay (Namibia).
- Financing and Development:
- The railway project is estimated to cost $1.5 billion, with additional traction investments of over $130 million.Botswana and Zambia are co-financing the project, with a Memorandum of Understanding (MoU) signed with Turkish firm Eksen Group to facilitate planning, preparation, and implementation.
- A bilateral agreement in March 2024 initiated a bankable feasibility study, with construction expected to progress by early 2026.
- Economic and Strategic Goals:
- The railway aims to reduce freight transport costs, attract investment, and boost special economic zones in Botswana and Zambia.
- Zambia seeks to secure export routes for copper and cobalt, reducing reliance on road transport and improving access to Asian markets via the Indian Ocean.
- The project is designed to handle 7.5 million tonnes of freight annually to be economically viable, compared to the current 3.1 million tonnes of road freight crossing the bridge.
- Challenges and Considerations:
- The rail track on the bridge remains isolated, as it is not yet connected to either country’s railway network, and no clear timeline for full connectivity has been confirmed.
- Achieving the required freight volume of 7.5 million tonnes per year is a significant challenge, necessitating logistics reforms and increased trade.
- Geopolitical considerations influenced the bridge’s curved design to avoid Zimbabwean and Namibian waters, which may also impact rail planning to ensure the route remains bilateral.
Progress and Future Steps
- Current Status: The rail track on the Kazungula Bridge is in place but not operational, awaiting the completion of the connecting railway lines. Discussions between Botswana and Zambia are ongoing to finalize the timeline and implementation.
- Next Steps: The project is in the feasibility study phase, with groundbreaking for the railway expected by early 2026. Private partnerships, such as with Eksen Group, are being leveraged to advance the project.
- Regional Impact: The railway is expected to strengthen the North-South Corridor, part of the Trans-African Highway, enhancing trade efficiency and economic integration across SADC countries, including potential involvement of Zimbabwe in future phases.
This plan positions the Kazungula Bridge as a critical link in a multimodal transport corridor, with the rail component aimed at transforming regional trade dynamics, though its success hinges on overcoming logistical and financial challenges.SummaryThe Mosetse–Kazungula–Livingstone Railway project, including the rail track over the Kazungula Bridge, has the following planned timelines based on available information:
- March 2024: Bilateral agreement signed between Botswana and Zambia, initiating a bankable feasibility study.
- Early 2026: Expected groundbreaking for the construction of the 430-km railway connecting Mosetse (Botswana) to Livingstone (Zambia) via the Kazungula Bridge.
- No Confirmed Completion Date: While construction is anticipated to start in early 2026, no specific timeline for the railway’s completion or the operationalization of the rail track on the bridge has been publicly confirmed.